500
How can I change the foreground color of the HTML text or caption of the bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarCaption,TVariant("<bgcolor=FF0000> to do </bgcolor>"));
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarForeColor,TVariant(16777215));

499
How can I assign a tooltip to a bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarToolTip,TVariant("This is a bit of text that's displayed when the cursor hovers the bar"));

498
How can I vertically align the HTML text or caption of the bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->set_ItemHeight(h,32);
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarCaption,TVariant("<bgcolor=FF0000> to do </bgcolor>"));
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarVAlignCaption,TVariant(0));

497
How can I align the HTML text or caption of the bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarCaption,TVariant("<bgcolor=FF0000> to do </bgcolor>"));
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarHAlignCaption,TVariant(0));

496
How can I assign a text or some HTML caption to a bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarCaption,TVariant(" <bgcolor=FF0000>to do</bgcolor> "));

495
How can I change the ending date of the bar in the chart
Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarEnd,TVariant(TDateTime(2001,1,6).operator double()));

494
How can I change the starting date of the bar in the chart
Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarStart,TVariant(TDateTime(2001,1,1).operator double()));

493
How can I change the style or the name of the bar in the chart

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarName,TVariant("Progress"));

492
How can I access properties and methods of the bar in the chart
Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->set_ItemBar(h,TVariant("K1"),Exganttlib_tlb::ItemBarPropertyEnum::exBarName,TVariant("Progress"));

491
How can I remove all bars in the item
Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->ClearBars(h);

490
How can I remove a bar from the chart
Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	long h = var_Items->AddItem(TVariant("Task 1"));
	var_Items->AddBar(h,TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("K1"),TNoParam());
	var_Items->RemoveBar(h,TVariant("K1"));

489
How can I add a bar and some text inside, in the chart area

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Task 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TNoParam(),TVariant(" to do "));

488
How can I add a bar and some text inside, in the chart area

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Task 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,6).operator double()),TNoParam(),TVariant("<bgcolor=FF0000> to do </bgcolor>"));

487
How can I add an anchor or a hyperline in the chart area

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Task 1")),TVariant(""),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TNoParam(),TVariant("just a <a1>link</a>"));

486
How can I add some text or captions in the chart area

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Task 1")),TVariant(""),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TNoParam(),TVariant("just a <b>caption</b>"));

485
How can I add a bar in the chart area

Gantt1->Columns->Add(L"Task");
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Task 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

484
Is there any option to put a picture or an icon to the thumb part of the scroll bar

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Gantt1->ScrollPartCaption[Exganttlib_tlb::ScrollBarEnum::exHChartScroll,Exganttlib_tlb::ScrollPartEnum::exThumbPart] = L"<img>1</img>";
Gantt1->ScrollThumbSize[Exganttlib_tlb::ScrollBarEnum::exHChartScroll] = 24;

483
How can I scroll fast the chart, or page by page

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Gantt1->ScrollHeight = 20;
Gantt1->ScrollButtonWidth = 20;
Gantt1->AllowChartScrollPage = true;
Gantt1->ScrollPartCaption[Exganttlib_tlb::ScrollBarEnum::exHChartScroll,Exganttlib_tlb::ScrollPartEnum::exLeftB5Part] = L"<img>1</img>";
Gantt1->ScrollPartCaption[Exganttlib_tlb::ScrollBarEnum::exHChartScroll,Exganttlib_tlb::ScrollPartEnum::exRightB1Part] = L"<img>2</img>";

482
How can I scroll fast the chart, or page by page

Gantt1->ScrollButtonWidth = 16;
Gantt1->AllowChartScrollPage = true;
Gantt1->ScrollPartCaption[Exganttlib_tlb::ScrollBarEnum::exHChartScroll,Exganttlib_tlb::ScrollPartEnum::exLeftB5Part] = L"<<";
Gantt1->ScrollPartCaption[Exganttlib_tlb::ScrollBarEnum::exHChartScroll,Exganttlib_tlb::ScrollPartEnum::exRightB1Part] = L">>";

481
How can I scroll fast the chart, or page by page

Gantt1->AllowChartScrollPage = true;

480
How can I display years, from 3 to 3

Gantt1->Chart->UnitWidth = 64;
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(0);
	var_Level->set_Label(TVariant("<%yyyy%>"));
	var_Level->Unit = Exganttlib_tlb::UnitEnum::exYear;
	var_Level->Count = 3;

479
How can I display years

Gantt1->Chart->UnitWidth = 64;
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(0);
	var_Level->set_Label(TVariant("<%yy%>"));
	var_Level->Unit = Exganttlib_tlb::UnitEnum::exYear;

478
How can I display years

Gantt1->Chart->UnitWidth = 48;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(0));

477
How can I display months, from 3 to 3

Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->UnitWidth = 64;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%mmmm%>"));
	var_Level->Unit = Exganttlib_tlb::UnitEnum::exMonth;
	var_Level->Count = 3;

476
How can I display months

Gantt1->Chart->UnitWidth = 64;
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%mmmm%>/<%yy%>"));
	var_Level->Unit = Exganttlib_tlb::UnitEnum::exMonth;

475
How can I display months

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->UnitWidth = 64;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(16));

474
How can I display weeks

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->UnitWidth = 64;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(17));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(256));

473
How can I display weeks

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(17));
Gantt1->Chart->get_Level(1)->set_Label(TVariant("<%ww%>"));

472
How can I display days, from 2 to 2

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(256));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%dd%>"));
	var_Level->Count = 2;

471
How can I display days

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(256));
Gantt1->Chart->get_Level(1)->set_Label(TVariant("<%dd%>"));

470
How can I display days

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(256));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(4096));

469
How can I display hours, from 6 to 6

Gantt1->Chart->set_FirstVisibleDate(TVariant("00:00"));
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(4096));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%hh%>"));
	var_Level->Count = 6;

468
How can I display hours

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(4096));
Gantt1->Chart->get_Level(1)->set_Label(TVariant("<%hh%>"));

467
How can I display hours

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(4096));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(65536));

466
How can I display minutes, from 15 to 15

Gantt1->Chart->set_FirstVisibleDate(TVariant("00:00"));
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(65536));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%nn%>"));
	var_Level->Count = 15;

465
How can I display minutes

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(65536));
Gantt1->Chart->get_Level(1)->set_Label(TVariant("<%nn%>"));

464
How can I display minutes

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->UnitWidth = 64;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(65536));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(1048576));

463
How can I display seconds, from 15 to 15

Gantt1->Chart->set_FirstVisibleDate(TVariant("00:00"));
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1048576));
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->set_Label(TVariant("<%ss%>"));
	var_Level->Count = 15;

462
How can I display seconds

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1048576));
Gantt1->Chart->get_Level(1)->set_Label(TVariant("<%ss%>"));

461
How can I display seconds

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->set_Label(TVariant(1048576));
Gantt1->Chart->get_Level(1)->set_Label(TVariant(16777216));

460
How can I align the text being shown in the chart's header

Gantt1->Chart->UnitWidth = 64;
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(0);
	var_Level->set_Label(TVariant("<b><%mmmm%></b> <r><%m%>"));
	var_Level->Unit = Exganttlib_tlb::UnitEnum::exMonth;
	var_Level->Alignment = Exganttlib_tlb::AlignmentEnum::LeftAlignment;

459
How can I hide the tooltip being displayed in the chart's header

Gantt1->Chart->get_Level(0)->set_ToolTip(TVariant(""));

458
How can I change the tooltip being displayed in the chart's header

Gantt1->Chart->get_Level(0)->set_ToolTip(TVariant("This is a bit of text that's shown when the cursor hovers the level"));

457
How can I change the visual appearance of the chart's header, where levels are displayed, using your EBN files

Gantt1->VisualAppearance->Add(1,TVariant("c:\\exontrol\\images\\normal.ebn"));
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->BackColorLevelHeader = 0x1000000;

456
How can I change the level's foreground color in the chart

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->ForeColor = RGB(255,0,0);
Gantt1->Chart->get_Level(1)->ForeColor = RGB(0,0,255);

455
How can I change the level's background color in the chart

Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(0)->BackColor = RGB(255,0,0);

452
How can I add icons or pictures to the scale or zoom area

Gantt1->HTMLPicture[L"pic1"] = TVariant("c:\\exontrol\\images\\zipdisk.gif");
Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewHeight = 48;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exZoomOnRClick;
	var_Chart->OverviewZoomCaption = L"Year|½Year|¼Year|<img>3</img> Week|Third|<img>2</img> Day|<img>pic1</img>|Hour|Min|Sec";
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exThirdMonth,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHour,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exMinute,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exSecond,L"");
	var_Chart->OverviewZoomUnit = 52;
Gantt1->Columns->Add(L"");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->set_CellSingleLine(TVariant(var_Items->AddItem(TVariant("Right click the Overview area and select a new scale"))),TVariant(0),Exganttlib_tlb::CellSingleLineEnum::exCaptionWordWrap);

451
How can I add icons or pictures to the scale or zoom area

Gantt1->HTMLPicture[L"pic1"] = TVariant("c:\\exontrol\\images\\zipdisk.gif");
Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewHeight = 48;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exAlwaysZoom;
	var_Chart->OverviewZoomCaption = L"Year|½Year|¼Year|<img>3</img> Week|Third|<img>2</img> Day|<img>pic1</img>|Hour|Min|Sec";
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exThirdMonth,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHour,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exMinute,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exSecond,L"");
	var_Chart->OverviewZoomUnit = 52;

450
How can I change the width of the unit in the scale or zoom

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exAlwaysZoom;
	var_Chart->OverviewZoomCaption = L"Year|½Year|¼Year|<img>3</img>|Third|<img>2</img>|<img>1</img>|Hour|Min|Sec";
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exThirdMonth,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHour,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exMinute,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exSecond,L"");
	var_Chart->OverviewZoomUnit = 24;

449
How can I a scale or zoom of the chart, when right clicking the chart's header

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exZoomOnRClick;
	var_Chart->OverviewZoomCaption = L"Year|½Year|¼Year|<img>3</img>Month|Third|<img>2</img>Week|<img>1</img>Day|Hour|Min|Sec";
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exThirdMonth,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHour,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exMinute,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exSecond,L"");
	var_Chart->OverviewZoomUnit = 64;
Gantt1->Columns->Add(L"");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->set_CellSingleLine(TVariant(var_Items->AddItem(TVariant("Right click the Overview area and select a new scale"))),TVariant(0),Exganttlib_tlb::CellSingleLineEnum::exCaptionWordWrap);

448
How can I a customize the scale or zoom of the chart

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exAlwaysZoom;
	var_Chart->OverviewZoomCaption = L"Year|½Year|¼Year|<img>3</img>Month|Third|<img>2</img>Week|<img>1</img>Day|Hour|Min|Sec";
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exThirdMonth,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exHour,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exMinute,L"");
	var_Chart->set_Label(Exganttlib_tlb::UnitEnum::exSecond,L"");
	var_Chart->OverviewZoomUnit = 64;

447
How can I a scale or zoom the chart at runtime

Gantt1->Images(TVariant(String("gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq") +
"lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" +
"0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" +
"NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA="));
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exAlwaysZoom;
	var_Chart->OverviewZoomCaption = L"½Year|¼Year|<img>3</img>Month|Third|<img>2</img>Week|<img>1</img>Day|Hour|Min|Sec";

446
How can I a scale or zoom the chart at runtime

Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
	var_Chart->AllowOverviewZoom = Exganttlib_tlb::OverviewZoomEnum::exAlwaysZoom;
	var_Chart->OverviewZoomUnit = 24;

445
How can I a programmatically select a date
Gantt1->Chart->MarkSelectDateColor = RGB(255,0,0);
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->set_SelectDate(TDateTime(2001,1,2).operator double(),true);
Gantt1->Chart->set_SelectDate(TDateTime(2001,1,5).operator double(),true);
Gantt1->Chart->SelectLevel = 0;

444
How can I change the color to select a date, when clicking the chart's header
Gantt1->Chart->BackColor = RGB(255,255,255);
Gantt1->Chart->MarkSelectDateColor = RGB(255,0,0);

443
How can I enable or disable selecting a date, when clicking the chart's header
Gantt1->Chart->BackColor = RGB(255,255,255);
Gantt1->Chart->MarkSelectDateColor = RGB(255,255,255);

442
How can I specify the color or the stype for non working hours

Gantt1->Chart->UnitScale = Exganttlib_tlb::UnitEnum::exHour;
Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->NonworkingHours = 127;
Gantt1->Chart->NonworkingHoursPattern = Exganttlib_tlb::PatternEnum::exPatternYard;
Gantt1->Chart->NonworkingHoursColor = RGB(255,0,0);

441
How can I specify the pattern or the stype for non working hours

Gantt1->Chart->UnitScale = Exganttlib_tlb::UnitEnum::exHour;
Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->NonworkingHours = 127;
Gantt1->Chart->NonworkingHoursPattern = Exganttlib_tlb::PatternEnum::exPatternDiagCross;

440
How can I specify the non working hours

Gantt1->Chart->UnitScale = Exganttlib_tlb::UnitEnum::exHour;
Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->NonworkingHours = 127;

439
How can I get the index of the level from the point or cursor
long var_LevelFromPoint = Gantt1->Chart->get_LevelFromPoint(0,0);

438
How can I get the link from the point or cursor
TVariant var_LinkFromPoint = TVariant(Gantt1->Chart->get_LinkFromPoint(0,0));

437
How can I check or verify if a date is a non working day
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(PChar(Gantt1->Chart->get_IsNonworkingDate(TVariant(TDateTime(2001,1,1).operator double()))));

436
How can I check or verify if a date fits the chart's visible area
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(PChar(Gantt1->Chart->get_IsDateVisible(TVariant(TDateTime(2001,1,1).operator double()))));

435
How can I add a remove all non working days
Gantt1->Chart->NonworkingDays = 0;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->AddNonworkingDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->ClearNonworkingDates();

434
How can I add a remove a non working days
Gantt1->Chart->NonworkingDays = 0;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->AddNonworkingDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->RemoveNonworkingDate(TVariant(TDateTime(2001,1,1).operator double()));

433
How can I add a custom non working days

Gantt1->Chart->NonworkingDays = 0;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->AddNonworkingDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Chart->AddNonworkingDate(TVariant(TDateTime(2001,1,5).operator double()));

432
How can hide the non working days
Gantt1->Chart->ShowNonworkingDates = false;

431
How can hide the non working days
Gantt1->Chart->NonworkingDays = 0;

430
How can I change the width of the links between bars

Gantt1->Chart->LinksStyle = Exganttlib_tlb::LinkStyleEnum::exLinkSolid;
Gantt1->Chart->LinksWidth = 2;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("B1"),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 2")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TVariant("B2"),TNoParam());
	var_Items->AddLink(TVariant("L1"),var_Items->get_FindItem(TVariant("Item 1"),TVariant(0),TNoParam()),TVariant("B1"),var_Items->get_FindItem(TVariant("Item 2"),TVariant(0),TNoParam()),TVariant("B2"));

429
How can I change the style for the links between bars

Gantt1->Chart->LinksStyle = Exganttlib_tlb::LinkStyleEnum::exLinkDashDotDot;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("B1"),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 2")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TVariant("B2"),TNoParam());
	var_Items->AddLink(TVariant("L1"),var_Items->get_FindItem(TVariant("Item 1"),TVariant(0),TNoParam()),TVariant("B1"),var_Items->get_FindItem(TVariant("Item 2"),TVariant(0),TNoParam()),TVariant("B2"));

428
How can I change the color for the links between bars

Gantt1->Chart->LinksColor = RGB(255,0,0);
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("B1"),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 2")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TVariant("B2"),TNoParam());
	var_Items->AddLink(TVariant("L1"),var_Items->get_FindItem(TVariant("Item 1"),TVariant(0),TNoParam()),TVariant("B1"),var_Items->get_FindItem(TVariant("Item 2"),TVariant(0),TNoParam()),TVariant("B2"));

427
How can I hide the links between bars
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TVariant("B1"),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 2")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TVariant("B2"),TNoParam());
	var_Items->AddLink(TVariant("L1"),var_Items->get_FindItem(TVariant("Item 1"),TVariant(0),TNoParam()),TVariant("B1"),var_Items->get_FindItem(TVariant("Item 2"),TVariant(0),TNoParam()),TVariant("B2"));
Gantt1->Chart->ShowLinks = false;

426
How can I display some grid line in the overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewLevelLines = 0;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TNoParam(),TNoParam());

425
How do I change the tooltip when the cursor hovers the overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewToolTip = L"Tooltip on the overview";
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,6).operator double()),TVariant(TDateTime(2001,1,14).operator double()),TNoParam(),TNoParam());

424
How do I remove the tooltip when the cursor hovers the overview area
Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewToolTip = L"";
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

423
How do I change the selection color in the overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewSelBackColor = RGB(255,0,0);
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

422
How do I change the background color for the overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewBackColor = RGB(255,0,0);
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

421
How do I specify the height for the overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->OverviewHeight = 16;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

420
How do I show or hide the control's overview area

Gantt1->Chart->OverviewVisible = Exganttlib_tlb::OverviewVisibleEnum::exOverviewShowAll;
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("Task"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

419
How do I get the bar from the point or cursor
TVariant var_BarFromPoint = TVariant(Gantt1->Chart->get_BarFromPoint(0,0));

418
How do I specify the color of pattern for non working days

Gantt1->Chart->NonworkingDays = 66;
Gantt1->Chart->NonworkingDaysPattern = Exganttlib_tlb::PatternEnum::exPatternVertical;
Gantt1->Chart->NonworkingDaysColor = RGB(255,0,0);

417
How do I specify the type of pattern for non working days

Gantt1->Chart->NonworkingDays = 66;
Gantt1->Chart->NonworkingDaysPattern = Exganttlib_tlb::PatternEnum::exPatternBrick;

416
How do I specify the non working days

Gantt1->Chart->NonworkingDays = 66;

415
How do I specify the non working days
Gantt1->Chart->NonworkingDays = 66;

414
How do I add a predefined bar

Gantt1->Chart->Bars->Add(L"CustomBar")->Color = RGB(255,0,0);
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2001,1,1).operator double()));
Gantt1->Columns->Add(L"Column");
Exganttlib_tlb::IItemsPtr var_Items = Gantt1->Items;
	var_Items->AddBar(var_Items->AddItem(TVariant("Item 1")),TVariant("CustomBar"),TVariant(TDateTime(2001,1,2).operator double()),TVariant(TDateTime(2001,1,4).operator double()),TNoParam(),TNoParam());

413
How do I change the unit being displayed in the chart

Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->UnitScale = Exganttlib_tlb::UnitEnum::exWeek;
Gantt1->Chart->UnitWidth = 64;

412
How do I specify the prodefined tooltip being shown on the chart's header, when Zoom method is used

Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exMonth,L"<%m3%>");
Gantt1->Chart->set_LabelToolTip(Exganttlib_tlb::UnitEnum::exMonth,L"Tooltip: <%mmmm%>");
Gantt1->Chart->Zoom(TDateTime(2007,1,1).operator double(),TDateTime(2008,1,1).operator double(),TNoParam());
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2007,1,1).operator double()));

411
How do I specify the prodefined labels being displayed on the chart, when Zoom method is used

Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exMonth,L"<%m3%>");
Gantt1->Chart->Zoom(TDateTime(2007,1,1).operator double(),TDateTime(2008,1,1).operator double(),TNoParam());
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2007,1,1).operator double()));

410
How do I scale or zoom the chart to a specified range of date
Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exHalfYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exQuarterYear,L"");
Gantt1->Chart->set_Label(Exganttlib_tlb::UnitEnum::exMonth,L"<%m3%>");
Gantt1->Chart->Zoom(TDateTime(2007,1,1).operator double(),TDateTime(2008,1,1).operator double(),TNoParam());
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2007,1,1).operator double()));

409
How do I scale or zoom the chart to a specified range of date
Gantt1->Chart->set_PaneWidth(false,0);
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->Zoom(TDateTime(2007,1,1).operator double(),TDateTime(2007,7,1).operator double(),TNoParam());
Gantt1->Chart->set_FirstVisibleDate(TVariant(TDateTime(2007,1,1).operator double()));

408
How do I find the next date or previous date
Exganttlib_tlb::IChartPtr var_Chart = Gantt1->Chart;
	var_Chart->set_FirstVisibleDate(TVariant(var_Chart->get_NextDate(TDateTime(2002,1,1).operator double(),Exganttlib_tlb::UnitEnum::exDay,TVariant(1))));

407
How can I change the color for the grid lines in the chart

Gantt1->Chart->DrawGridLines = Exganttlib_tlb::GridLinesEnum::exAllLines;
Gantt1->Chart->LevelCount = 2;
Exganttlib_tlb::ILevelPtr var_Level = Gantt1->Chart->get_Level(1);
	var_Level->DrawGridLines = true;
	var_Level->GridLineColor = RGB(255,0,0);

406
How can I draw, show or hide the grid lines in the chart

Gantt1->Chart->DrawGridLines = Exganttlib_tlb::GridLinesEnum::exAllLines;
Gantt1->Chart->LevelCount = 2;
Gantt1->Chart->get_Level(1)->DrawGridLines = true;

405
How do I change the color to highlight the today in the chart

Gantt1->Chart->MarkTodayColor = RGB(255,0,0);

404
How do I hide or stop highlighting the today area in the chart
Gantt1->Chart->BackColor = RGB(255,255,255);
Gantt1->Chart->MarkTodayColor = RGB(255,255,255);

403
Is there any function to get the date in the format that I use for levels, to layout my chart's header
String h = Gantt1->Chart->get_FormatDate(TDateTime(2002,1,1).operator double(),L"<%yyyy%> <%mmmm%> <%d%> <%dddd%>");
Gantt1->Columns->Add(L"h");

402
How can I get the date from the point, cursor
// MouseMove event - Occurs when the user moves the mouse.
void __fastcall TForm1::Gantt1MouseMove(TObject *Sender,short   Button,short   Shift,int   X,int   Y)
{
	OutputDebugString( PChar(Gantt1->Chart->get_DateFromPoint(-1,-1)) );
}


401
How can I show or hide the small ticker that shows up when the cursor hovers the chart area
Gantt1->Chart->DrawDateTicker = false;